| Proceedings
of the Seminar on Integrity Pact dated 27th
May 2005 at SPIPA, Ahmedabad.

A
one–day seminar on Integrity Pact was organized by Gujarat
Vigilance Commission 0n May 27, 2005at Sardar Patel
Institute of Public Administration (SPIPA), Ahmedabad.
The seminar was inaugurated by Shri P. Shankar, the
Chief Vigilance Commissioner by lighting a lamp.
Welcoming
the participants, Dr. Ashok Narayan, Vigilance Commissioner,
Gujarat State, explained the
importance of preventive vigilance as opposed to a purely
complaint-based approach, which, though necessary is
inadequate to deal with the problem of corruption. Preventive
vigilance includes improvement in systems and procedures
to make them more and more transparent and simplify
minimizing the scope of corruption. Public tendering/contracting
is one important area, which is very often the sources
of corruption and malpractices. Integrity Pact (IP)
is a device, which introduces a 'code of conduct', applicable
equally to the Principal and bidders. He gave a brief
overview of the concept of IP. A model IP had been made
available by the Transparency International (TI), which
had been circulated to the participants well in advance
(Annexure I).
He also requested the Transparency International (TI)
to present specific case studies pertaining to actual
implementation of IP indicating the kind of problems
which actually arose from time to time during its implementation
and how they were tackled within the framework of IP.
He hoped that the seminar would pave the way for a concrete
model of IP, to be implemented by the Government of
Gujarat and its PSU’s.
Admiral Tahiliani from Transparency International (India)
gave the keynote address. A copy of his presentation
is at Annexure-II.
He gave the figures that India
is the 90th most corrupt nation in the world
(out of 143 nations) and 5% of the world GDP being diverted
to corrupt practices. He also mentioned that the corruption
is the highest in arms-trade (in which 50% of bribes
are given in international transactions) followed by
infrastructure and construction.
He
emphasized that the IP cannot be effective unless all
the parties consisting of Government and Government
officials involved and all the bidders or prospective
bidders are a party to it. The pact has to remain in
force starting from the pre-bidding stage through the
contractive period up to the implementation of the entire
project. The role of the representatives of the civil
society is very crucial in constant monitoring of the
tendering process. Any violations of the pact would
invite sanctions applicable to Government officials
as well as to the bidders. The violations of the integrity
pact need not be proved in the strict judicial sense
but must be established beyond any reasonable doubt.
The disputes are to be resolved by national or international
arbitration. However, when the spirit of the integrity
pact catches up, arbitration is seldom necessary. Admiral
Tahiliani stated that ONGC has decided to introduce
the integrity pact with effect from July 1, 2005 and
efforts are being made to introduce it in certain Ministries
of GOI, for example in Defense Ministry. Admiral Tahiliani
also stated that the model IP, which he has sent to
Vigilance Commission and which had been circulated to
the participants in the seminar is still being worked
upon to suit Indian conditions and that he would be
sending a revised model of integrity pact along with
specific case-studies highlighting how the IP have been
implemented, what problems arose during its implementation
and how exactly they were taken care of.
Shri Sudhir Mankad, Chief Secretary to Government of
Gujarat, stated that the IP should not merely consist
of a simplistic statement on the part of the Government
and bidders not to take or accept bribes. This would
be hardly enough. He emphasized that individual honesty
of officials concerned is more important than the systems
and procedures. He wondered whether it was necessary
to negotiate only with L1. He gave examples of how,
by a judicious deviation from the rules and procedures,
he was able to arrive at decisions, which saved a lot
of money for the Government. He also emphasized the
need to make the tender procedures more and more transparent
by putting tenders, price bids, proceedings of technical
scrutiny; the details of the party finally awarded the
contract etc. on the web site. He also mentioned how
making the transfers of primary teachers totally transparent
to public by having a camp approach had minimized corruption.
He also made the point that an impression is sometimes
conveyed that corruption is a phenomenon only of government
and public sector enterprises. This is not true. There
is a lot more corruption in private sector than in government
and public sector. That also should be tackled. For
instance, the law of disproportionate assets should
be made applicable to private sector also.
Shri
B.R. Lall from TI disagreed with Shri Sudhir Mankad
that L1 should not have any sanctity. He said that one
has to accept L1 but a proper analysis has to be there
to ensure that L1 is comparable to all other bids with
the same quality and other specifications. He mentioned
that in the construction sector corruption starts right
from the planning and designing stage and continues
through every stage in award, execution and maintenance.
Collusion (cartelization) on the part of contractors
is the main problem. Efforts are made not to issue tender
forms to those who may be the real competitors, excluding
the potential L1 in pre-qualification, inflate estimates
deliberately, using retail rates in plans and estimates
which are higher than the wholesale rates, projecting
productivity at lower level, misusing escalation clause,
concealing substandard work, deliberately lowering specifications
etc.. These malpractices are done either due to dishonest
intention or under extraneous pressure.
IP is workable because when the parties are brought
face to face, it becomes a solemn commitment. For the
IP to work properly, all the data should be put on the
website accessible by all. The IP is useful at every
stage of construction. He mentioned that there was a
view that in place of pre-qualification there could
be a post-bid qualification. He suggested that design
and execution should never be with the same company.
The text of his presentation is at Annexure-III.
Shri AK Luke, MD, Gujarat State Fertilizer Company intervened
to say that it was always possible for persons with
integrity beyond doubt, to make procedural mistakes.
Therefore he suggested that while making out a case
of corruption against public servants, assets, (disproportionate
to income) should be targeted rather than the procedural
mistake. To put it briefly, the malafide intention is
what needs to be established. He also mentioned that
according to an estimate approx. 2550 billion dollars
were stacked up in various Swiss bank accounts by Indians
living in India.
These are the kind of issues which need to be targeted.
Shri Arun Duggal from TI made the point that IP is a
tool for changing the entire working culture of the
govt. This had happened in 14 countries, which have
introduced and implemented the IP. But the implementing
organizations need to have immense clarity about the
code of conduct involved. The role of monitor
is very important. He should be a knowledgeable person
and should be beyond controversies in which both the
parties should have confidence. The entire process should
be transparent to the public. It is a tool that
will eventually lead to economic growth. He was confident
that Gujarat would take the lead and would play a
role of model State, in this field also, as it had already
done in many fields of social and economic development.
Shri P.K. Laheri, CMD of Sardar Sarovar Narmada Nigam
Limited (SSNL) welcomed the effort of Gujarat Vigilance
Commission (GVC) to focus attention on the concept of
IP which is a matter of considerable public importance
and to discuss it in a forum consisting of knowledgeable
experts and experienced and leading citizens. Transparency
International (TI) had been engaged in conducting surveys
of the levels of corruption in different countries.
Looking to the situation there was a need to improve
our countries image, he said.
He
enumerated the advantages of the given IP model as:
- It
is open, i.e. it brings the contracting parties
face to face.
- It
is an agreement that is mutually arrived at.
- It
is very comprehensive.
However,
it needs to address the issue of cartelization and collusion.
He recommended that the agreement must contain a declaration
by the bidder that he is not a member of any cartel.
It should also contain a responsibility clause by the
bidder for maintaining the declared and accepted quality
and specifications. The IP should be so formulated that
all the loopholes which leave room for corruption are
effectively plugged by including items such as price
escalation in exceptional circumstances, extra items,
extension of time limit etc. Very often delay in the
implementation of the project could jack up the cost
of the project substantially and SSNL was a glaring
example of this phenomenon. Too much manpower also would
create similar problems. Very often there are very few
offers which fulfill the quality standards. The specifications
should be mentioned in the tender in as much detail
as possible. The ‘dos and don’ts’ should be equally
applicable to both the parties.
He
announced that SSNL was committed to the concept and
was going to introduce IP in a suitable form.
Shri VRS Cowlagi, former Vigilance Commissioner, Gujarat
said that IP is an innovative idea. He mentioned that
Gujarat State Fertilizer Company (GSFC) had already
introduced an ‘Ethics Pact’ (a copy of the brief statement
of the Ethics Pact is at Annexure II), which is a very
good beginning. He emphasized that the past experiences
must be taken into account.
Gujarat
has a very favourable environment for introduction of
any innovative idea such as IP. Even the presence of
a monitor or ombudsman would be sufficient
make the difference. The concept of social audit
also needs to be developed. He gave an example to show
how the unit cost of the same work in the same area
used to be different for works undertaken by different
departments. At the intervention of GVC and exercise
was undertaken to have a uniform unit cost for similar
work to be adopted by different departments. He also
feared that in spite of IP, the losing bidders would
have a tendency to go for litigation. This had to be
taken care of in some way. While imposing sanctions,
there should not be a blanket debarring of the bidder,
but only for specified work. Blacklisting of bidders
as of applicants was also a questionable practice, which
would not stand the test of a court of law. He also
pointed out that the courts had often ruled that any
provisions of a contract which impinged on somebody’s
legal and fundamental right would not be enforceable.
This would have to be kept in mind while drafting the
IP
Shri
B.J. Vasavada, retired member-secretary, Gujarat Water
and Sewerage Board mentioned that integrity, quality,
fairness, transparency and objectivity are the fundamental
principles, which go to the root of successful performance
and installing public confidence. He welcomed the concept
of IP and made the following suggestions:-
i.
While it is a positive step that the bidder/contractor
should be disqualified if the IP is violated, it would
be appropriate to have a Dispute Resolution Board consisting
of independent representative nominated by each party
as a part of the bid document and tender document, to
ensure that corrupt and fraudulent practices are not
resorted to while imposing sanctions on bidders through
contractors.
ii. Just
as the model IP circulated provides for compensation
for damages by the bidder to the principal, it is also
necessary to make the principal responsible for similar
compensation of damages if it is proved that the contractor
was wrongly disqualified or excluded from the contract.
iii. All
project-implementing authorities should be made responsible
to provide and maintain a record of fraudulent and corrupt
practices adopted by the contractors. Similarly, Contractors
should be given an opportunity to be informed the names
and designations of the officers practicing corrupt
and fraudulent practices.
iv. The
concept of independent monitor is very good but there
is a possibility of the monitor himself getting corrupted.
Therefore it could be better to have a Board of Monitors
with representation from the contractor, the principal,
civil society from amongst persons of high professional
integrity status, knowledge, experience, expertise and
recognition.
The
text of Shri Vasavada's presentation is at Annexure-IV.
Shri
H Dora, Vigilance Commissioner (CVC) gave a detailed
account of steps taken by CVC to make the process of
tendering transparent at all levels by making extensive
use of technology. He mentioned that instructions have
been given to Central Public Sector Undertakings to
resort to 'e-bidding' by putting the tender on
website, the details of technical scrutiny and final
bidding on the web site. Even the system of ‘e-payments’
should be adopted. He mentioned the point that system
improvements are very important because systems are
meant for the conformists.
Admiral Tahiliani intervened to emphasize that system
improvements are very essential to curb the corruption
and they could not be ignored.
Shri
P. Shankar, CVC, also emphasized the overall need of
systems and procedures. He mentioned that the Transparency
International has been advocating the implementation
of IP. The matter was discussed also in the Advisory
Council of the CVC. As a result of this, efforts are
being made to introduce the IP in Central Ministries
and PSUs. A similar Seminar was organized at Bangalore
on 10-5-2005
to discuss the concept of IP in detail with Central
PSUs and some of the Central Ministries. As a result,
ONGC has already decided to introduce the IP and some
ministries are making efforts in this direction.
He also clarified that the sanctity of the L1 did not
imply that no other factors should be taken into consideration.
All the bidders have to pass through the pre-qualification
stage and technical scrutiny. The bidders who do not
satisfy the specification or other requirements of tender
inquiry need not be considered at all. Among those who
satisfy the specifications, undoubtedly the L1 must
be preferred. There may be examples where money could
be saved by having negotiations with parties other than
L1, but he was very clear that this would breach the
sanctity of the tender process and could lead to unfair
practices. Altering the tender conditions or specifications
after the tender had been floated and bids had been
received should never be permitted. The specifications
indicating the standards of quality required must be
mentioned in the tender notice clearly and should not
be altered later.
Shri Varesh Sinha, Principal Secretary, Panchayat, Rural
Housing & Rural Development Department, intervened
to say that he welcomed the concept of IP and would
take steps to introduce it in District Panchayats and
Taluka Panchayats.
Smt. Anita Karwal, Additional Commissioner, SPIPA stated
that looking to the fact that the most important role
of implementing the IP is that of the monitor and that
he/she has to be chosen with great care, being a person
of impeccable integrity and expertise in the
areas of contact. It is recommended that the CVC
may empanel for such persons for the benefit of various
Government/Organizations desirous of taking up the IP
model for implementation.
It
was then suggested by CVC that it may be a good idea
to taking the assistance of TI in the process of making
a suitable panel of monitors.
Summing up the discussion, Dr. Ashok Narayan, Vigilance
Commissioner, Gujarat State,
stated that improvement in systems and procedures by
making them simpler, easy to interpret and more transparent
is a very important aspect of preventive vigilance.
This is not to say that individuals are not important
or that no efforts should be made to improve their value
systems. However, that was quite another matter and
would require appropriate methods of recruitment and
appointment. There are public servants whose honesty
is always beyond doubt and they would remain honest
no matter what systems and procedures are. There are
yet others who would find a way of getting round any
systems and procedures and practice dishonesty. Still
there are a large number of public servants who are
fence sitters and would act dishonestly if the systems
and procedures permitted it. It is for them that the
systems and procedures are meant. It would be wrong
to over-generalize and glorify exceptions where deviating
from the prescribed rules and procedures, one was able
to save money. Even in such exceptions, the detailed
reasons must be recorded; otherwise it would be difficult
for the Vigilance Commission to understand the motive
behind deviating from standard procedures.
The IP is not merely a contract, it is a culture
and it is supposed to create an environment of mutual
trust and ethical behaviour. Therefore it can be
introduced in phases. A very necessary prelude to the
introduction of IP would be total transparency in the
tender procedure at every stage as many participants
emphasized. The tender notice, the bids, the proceedings
of technical scrutiny, the price bids received and the
details of the winning bid........ all these could be
made known to the public through web site. After this,
one may move towards the drafting of a suitable pact
and involvement of the representatives of civil society
as a monitor. The help of Transparency International
could be taken to identify the monitor from the civil
society. If the pact is implemented and monitored properly,
the need for arbitration would hardly arise.
He mentioned that the discussions in the seminar had
been extremely fruitful. Sardar Sarovar Narmada Nigam
Limited (SSNNL) and Panchayats, Rural Housing &
Rural Development Department (P,RH&RDD) have already
decided to introduce the IP and the GSFC had also made
a very good beginning in the form of 'Ethics Pact'.
Shri P. Shankar, CVC gave the valedictory address giving
the detailed account of the initiatives taken by Transparency
International and CVC in ensuring transparency and mutual
trust in the fields of public contract. He noted that
many useful points had been made in the seminar and
a better climate for introduction of IP has been
created in Gujarat. He was also happy to note that
SSNNL and P,RH&RDD have already decided to introduce
the IP and many others are likely to fall in line. Things
could not be changed overnight but the concept has to
grow and gradually create a proper environment
The seminar ended with the vote of thanks from Shri
B.K. Bhatt, Secretary of the Gujarat Vigilance Commission.
The
seminar ended with a cordial vote of thanks.
List
of participants is at AnnexureV
As
approved by the Vigilance Commissioner, Gujarat.
(
B.K. Bhatt )
Secretary
GUJARAT
VIGILANCE COMMISSION
Gandhinagar.
|